Cucaracha Slide
The Canal Record - October 9, 1907
Notes of Progress.
The Cucaracha Slide at its Old Tricks.
Owing to the heavy rainfalls of the past few weeks, the Cucaracha slide, which remains
quiet during the dry season, has again begun to move. This slide is on the east side
of the Canal about half a mile south of Gold Hill, and first began to move in 1884 or
1885, during the time of the old French company. It gave this company a good deal of
trouble during the entire time that operations were in progress in this vicinity; but its
movement ceased soon after the failure of the old company in 1889. It remained
practically quiescent during the entire period of control by the new French company,
the reason being that no operations in the Canal in this vicinity were carried on by that
company. With the resumption of work by the United States in 1905, the slide again
began to move, and has continued to give more or less trouble during every wet season
since. The total amount of material in movement is estimated at about 500,000 cubic
yards. The plan pursued heretofore has been to attack the slide during the dry
season with steam shovels, cutting as wide a berm as possible in the material outside of
the limits of the prism, so that, during the wet season, the moving material would be
caught on the berms and would not get into the Canal. The movement during the
present season has been more rapid than usual and the berms have been filled up,
permitting a part of the material to get into the Canal prism. Shovel No. 223 was
caught by the moving mass of material on October 4, and was extricated unimpaired on
October 6. Shovel No. 109 was also caught, but was pulled out by the wrecking train
on October 5.
During the next dry season as many shovels as possible will be put to work outside of the
Canal prism, for the purpose of removing all the material now in motion, which would be
liable to get into the Canal during succeeding wet seasons. the total amount of
material involved in this slide (about 500,000 cubic yards) was included in the estimate
of April 1, 1907, which gave the total amount of material yet to be excavated in order to
complete the Canal under the existing project.
The Canal Record - October 16, 1907
Notes of Progress.
The Cucaracha Slide.
The work of removing the material east into the Culebra Cut by the Cucaracha slide has
continued without interruption day and night since the last issue of The Canal
Record, and several hundred cubic yards of material have been taken out. To
avoid delaying the movement of dirt trains a track is being laid from the bottom of the
Cut up to the second level on the west side.
This track will be completed in about a week, and when finished the movement of dirt
trains will cease to be effected by the slide. This will enable the work upon the
slide to be transacted more economically and without detriment to the other parts of the
work. Although causing some temporary annoyance until the present wet season ends,
the slide will in no way delay the completion of the Canal.
The Canal Record - October 23, 1907
Notes of Progress.
The Cucaracha Slide.
During the past week the work of removing the material east into Culebra Cut by the
Cucaracha slide has continued with undiminished energy. Electric arc lights have
been erected at the slide, and the work has been carried forward day and night with three
steam shovels. The effect of this has been to gain slowly but gradually on the
slide, and it is hoped that within ten days or two weeks the movement of material trains
through the Cut will be resumed on the old schedule. This gain has been achieved in
spite of the fact that during the last twenty days the rainfall has been the heaviest of
the year.
The Canal Record - October 30, 1907
Notes of Progress.
The Cucaracha Slide.
The work of removing the material east into the Cut by the Cucaracha slide has advanced
very favorably during the past week, and a steady gain upon the slide has been made.
On Sunday night about 900 cubic yards were taken out and on Monday more than 1,000
cubic yards. during the first two weeks the slide moved steadily toward the Cut at
the rate of about 14 feet per day, but this rate of motion has decreased in the past four
or five days.
One through track has been laid, and a second will be laid within the next few days if all
goes well. the movement of dirt trains through the cut will then be resumed.
Upon the whole the conditions regarding the slide are more favorable than was first
anticipated they could be at this time. The total amount of earth which will have to
be removed will probably be less than was first estimated. Steady progress has been
made in spite of the fact that the rains of the month have been the heaviest of the year.
The Canal Record - November 6, 1907
Notes of Progress.
The Cucaracha Slide.
Steady progress has been made during the past week in removing the material east into the
Cut by the Cucaracha slide. The work has been aided by the slow movement of the
slide which has dropped from 14 feet a day, the rate maintained during the first two
weeks, to about 4 feet a day. Two tracks have been laid past the foot of the slide
and a third track will be in place within a few days. The movement of dirt trains,
to the full capacity existing before the slide occurred, will then be resumed.
The Canal Record - November 13, 1907
Notes of Progress.
The Cucaracha Slide.
Owing to the progress made in the removal of earth from the Cucaracha slide, night work is
now no longer necessary. Two tracks are in operation at the slide in the Cut on the
west side, one of which is used for the passage of loaded material trains and the other as
the loading track for steam shovels. The passage of all loaded material trains through the
Cut to the south has been resumed, but in order to interfere as little as possible with
work at the slide, empty trains are brought back on the line of the Panama railroad.
[This the last mention of the Cucaracha Slide in the Canal Record regarding
this particular incident]